Cookies

We use essential cookies to make our site work. We'd also like to set analytics cookies that help us make improvements by measuring how you use the site. These will be set only if you accept.

For more detailed information about the cookies we use, see our cookies page.

Essential Cookies

Essential cookies enable core functionality such as security, network management, and accessibility. For example, the selections you make here about which cookies to accept are stored in a cookie.

You may disable these by changing your browser settings, but this may affect how the website functions.

Analytics Cookies

We'd like to set Google Analytics cookies to help us improve our website by collecting and reporting information on how you use it. The cookies collect information in a way that does not directly identify you.

Third Party Cookies

Third party cookies are ones planted by other websites while using this site. This may occur (for example) where a Twitter or Facebook feed is embedded with a page. Selecting to turn these off will hide such content.

Skip to main content

M3 junction 9 improvements project update - 13/10

By Belinda Baker, Parish Clerk Headbourne Worthy Parish Council

Monday, 13 October 2025

ABOUT THE AUTHOR

Headbourne Worthy Parish Council Contributor

VIEW ALL ARTICLES BY THIS AUTHOR

During mid-September the contractors successfully switched traffic into a contraflow system on the M3 southbound. They’ve now begun work to construct the new A34 underpass.

Through October 2025, they will continue to remove vegetation from various locations. Before any clearance begins, they carry out thorough ecological checks to identify wildlife and nesting birds.

Once work is complete, they will replant and deliver several environmental enhancements — including restoring chalk grassland habitats. Find out more about the Chalk Grassland restoration: Chalk Grassland factsheet.

  • Overnight on Tuesday 14, Wednesday 15 and Thursday 16 October they are closing the M3 southbound between junctions 8 and 9 (9pm to 6am) - Vegetation clearance and Vehicle Restraint System removal
  • On Friday 17 and Saturday 18 October they are closing the A34 at Three Maids Hill and A33 the Cart and Horse junction southbound (9pm to 6am) - A34 access construction
  • Overnight on Monday 20, Tuesday 21, Wednesday 22, and Thursday 23 October they are closing the M3 junction 9 northbound exit slip road (9pm to 6am) - Vegetation clearance
  • Overnight on Sunday 26 October they are closing the M3 junction 9 southbound entry slip road (9pm to 6am) - Vegetation clearance
  • Overnight on Monday 27, Tuesday 28, Wednesday 29, Thursday 30 and Friday 31 October they are closing the M3 northbound between junctions 9 and 8 (9pm to 6am) - Vegetation clearance

Our diversion routes are designed to suit all vehicle types.

We advise you not to use a Satnav when following any of our diversions because there is a risk it could direct you down an unsuitable road or back onto our network when it is closed.